Small power plant for a timber processing enterprise energy supply. Basic and detailed design
Разработка проектно-сметной документации для нового строительства и реконструкции действующих энергетических объектов и гражданского строительства
Small power plant for a timber processing enterprise energy supply. Basic and detailed design
2021
2,5
MW
Site location: village Chemdalsk, Evenki district, Krasnoyarsk Krai, RF
Client: JSC "Energy Solutions", Moscow
Design stages: Basic design, detailed design
The Project Technical and Economic Data
- Installed power:
- electric, MW - 2.5
- thermal, MW (Gcal/h) - 4.138 (3.558)
- Main equipment composition
- steam boiler (drum, fire tube) with a steam capacity of 13 t / h (10.8 MW), live steam pressure of 37 bar (e), temperature - 425° С
- steam turbine "M + M" condensing with intermediate steam extraction 12 bar (abs.), maximum power 2.65 MW
- The number of hours of work per year, h - at least 8400
- Annual energy production:
- electric, kW∙h - 17 950 684.93
- thermal (in network water), Gcal - 11 302.45
- Annual energy consumption for auxiliary needs, kW∙h (%) - 2 940 151, 20
- Annual energy supply:
- electric, kW∙h - 15 010 533.73
- thermal (in network water), Gcal - 10 304.65
- The number of hours of use of the installed capacity:
- electric, kW∙h/year - 7180.2739
- Annual consumption of fuel equivalent, t.f. - 14,020.5
- Specific consumption of equivalent fuel for supplied energy:
- electric, g.f./kW∙h - 560.43
- heat, kg.c.f./Gcal - 544.24
- Fuel type:
- main - wood waste from sawmill
- emergency - not provided
- Total number of personnel, people - 30
- Site area, ha - 1.13
- Building factor, % - 27.5
- Construction cost, thousand rubles - 838 460.162
Summary of key solutions
The small power plant is designed for generation of power and heat by burning wood chips and other waste from a sawmill in a boiler.