MS6001FA Gas Turbines Assembly & Tests Works

Разработка проектно-сметной документации для нового строительства и реконструкции действующих энергетических объектов и гражданского строительства

MS6001FA Gas Turbines Assembly & Tests Works

2015

The object location: Russian Federation, Yaroslavl region, Rybinsk town, Sysuivska str., part 28 (Eastern Industrial Area).

The Customer: «Russian Gas Turbines» LLC.

Designing Stages:

  • Conceptual Design Documentation.
  • Detailed Design Documentation of zero cycle of production and administrative building.

 

 

rybinskl2rybinskl3

 

 

 

 

 

 

 

 

 

 

The Project Technical-Economic Indices

  • Maximum production capacity, pcs/year - 20.
  • Enterprise operation mode - 5 days per week, 24 hours per day and night.
  • Total quantity of operation hours per year (regarding 249 working days in 2012), hours - 5976.
  • Electric power consumption for production and servicing needs, kW/h - 7500, including:
    - At the 1st Stage, kW/h - 2400,
    - At the 2nd Stage, kW/h - 5100.
  • Annual electric power consumption for turbine production, mln kW - 44.82. Electric power consumption for production and servicing needs, kW/h - 7500, including:
    - At the 1st Stage, kW/h - 2400,
    - At the 2nd Stage, kW/h - 5100.
  • Annual natural gas flow rate, thousands nm3 - 2275, thousands t.e.f.- 2.609, including:
    - For ventilation plants, thousands nm3 - 894.3 / 2 034, thousands t.e.f.- 1.026 / 2.334,
    - For gas turbines tests (the 2nd Stage), thousands nm3 - 240, thousands t.e.f.- 0.275.
  • Total staff, persons - 200/218.
  • Construction time period - 18/24.
  • Allotted ground area having been used, hа - 8.2355.
  • Land-to-Building Ratio, % - 41.


Brief Description of Main Solutions


The Works products are MS6001FA gas turbines of GE Energy Company. Designing and construction have been carried out in two stages.

The 1st Stage:

  • The production hall, including two buildings (the assembly workshop with the overhead cranes of the load-carrying capacity 50, 60 and 120t, the assembly stands and the spare parts store) of the plan dimensions 132 х 103m;
  • The administrative building with the office premises per 100 persons and the canteen;
  • The auxiliary buildings and structures (the gating system post, the stores, the fire-fighting pumping station with the reservoirs, the transformation substation, the treatment facilities etc.);
  • The inner-site roads, outdoor parking place;
  • The inner-site engineering networks.

The 2nd Stage:

  • The test stand building with the equipment and the auxiliary systems required for complex testing of the assembled turbines;
  • The gas preparation post;
  • The pressing-out compressor station;
  • The painting and packing shop.

The 1st Stage structures construction was completed in 2013; the 2nd Stage structures construction was completed in 2015.