Restoration of Monitoring & Control System with Simultaneous Implementation of PACS at the Power Generation Units Nos. 1-4 of the 1st turn of Reconstruction at Uglegorsk TPP Restoration

Разработка проектно-сметной документации для нового строительства и реконструкции действующих энергетических объектов и гражданского строительства

Restoration of Monitoring & Control System with Simultaneous Implementation of PACS at the Power Generation Units Nos. 1-4 of the 1st turn of Reconstruction at Uglegorsk TPP Restoration

The object location: Svetlodarsk town, Donetsk region, Ukraine.

The Customer: Uglegorsk TPP PJSC «Tsentrenergo».

Designing Stages:

  • Conceptual design documentation.
  • Detailed design documentation, including site supervisionр. 

uglegorsk1uglegorsk2

                                                  

                                                

 

 

 

 

 

 

 

The Project Technical-Economic Indices

  • Annual energy resource demand, t.e.f.- 150.
  • Software-Hardware complex - TREI-5B-05.

Brief Description of Main Solutions

   The refurbishment of the monitoring & control system is provided for based on the up-to-date micro-processor based devices. As the software-hardware complex of the control & monitoring system there has been used TREI-5B-05 of the TREI GMBH Company (Germany).

   Based on the results of the project review there have been obtained the Positive Opinions of SE «Ukrgosstroyekspertiza» branch in Donezk region, Account No.05-2065-13 dated 15.07.2013, Account No. 05-1890-15 dated 24.12.2015, Account No. 05-3942-13 dated 04.11.2013, Account No. 05-2064-13 dated 15.08.2013 for the power generation Units Nos. 1, 2, 3, 4 respectively.