South-Ukraine NPP. Power unit 3. Reconstruction of the K-1000-60/3000 turbogenerator control system. Detailed design
Разработка проектно-сметной документации для нового строительства и реконструкции действующих энергетических объектов и гражданского строительства
South-Ukraine NPP. Power unit 3. Reconstruction of the K-1000-60/3000 turbogenerator control system. Detailed design
2019-2020
1000
MW
Site location: Yuzhnoukrainsk, Mykolaiv region, Ukraine
Client: SE NNEGC Energoatom
Design stage: Detailed design
Scope of work:
To eliminate the flaws of the existing turbine automatic control and protection system, it is necessary to modernize its elements and components, taking into account modern technologies.
The detailed design provides for the replacement of the electrical equipment of the turbine ACPS.
Modernization of the electric part of turbine control system includes:
- replacement of TGI-3000-3 sensors with new angular velocity sensors;
- replacement of the electric part of turbine control system with a new software and hardware complex;
- installation of new position sensors on relief valves, on the heating steam valve SPP; ZhK TsVD, TsNT;
- installation of cabinets of normalizing converters for NP position sensors RK HPC, CNT, heating steam valves SPP, KS;
- installation of new electromechanical converters (EMC) complete with power supply cabinets.
The detailed design meets the requirements of Annexes E and G of DBN A.2.2-3:2014