Replacement of hot water boilers in the starting-up boiler house of the Kursk NPP

Разработка проектно-сметной документации для нового строительства и реконструкции действующих энергетических объектов и гражданского строительства

Replacement of hot water boilers in the starting-up boiler house of the Kursk NPP

2015
35 MW

Location of the facility: Russian Federation, Kursk Region, Kurchativ, Industrial Zone, Branch of Rosenergoatom Concern OJSC, Kursk NPP.

Customer: KomplektEnergo LLC, End Customer: Rosenergoatom Concern OJSC.

Design stages:

  • basic design
  • detailed design

Technical and economic indicators of projects

Indicator

Units

Value, indicator

Nominal heat output

MW (Gcal/year)

170

Тhe temperature of the mains water at the inlet

°С

70 (not less than 65)

Тhe temperature of the mains water at the outlet

°С

790

Range of regulation of heat output, in relation to the nominal

%

30 to 100

Main and reserve fuel

 

fuel oil grade M-100

Estimated efficiency of the boiler when operating on fuel oil

%

not less than 90,16

 

Brief description of the main decisions

Purpose of the object

The main goal of the project is to replace three network hot water boilers of the PTVM-30M-4 type with three Eurotherm 35 (KV-GM-35-150N) hot water boilers, which will restore the design total power of the PPH to 170 Gcal/h, as well as ensure safe operation of power units of the Kursk NPP in accordance with the RD for the safe operation of NPPs.

The main task is to eliminate the risk of a shortage of thermal energy during the decommissioning of units of the Kursk NPP.

Basic equipment

Three water-heating boilers of the Eurotherm 35 type (KV-GM-35-150N), manufactured by Safonovo Hiting Solutions OJSC.

The project is under implementation.